Annex (Expansion) Project Quarterly Report

Quarterly Progress Report ~ October 2025

  • Expansion fundraising as of October 2025: $1,370,050.
  • On October 8, the City of Fort Bragg Planning commission approved the final building plans for the Library Annex. A work agreement was signed with engineer, Dave Duncan.
  • Meeting with project manager, Cynthia Sharon, to establish a timeline for the Library Annes building project.
  • Held successful fundraisers a Café q and Westport Hotel. Continue promoting Library Annex with coin jars in local stores.
  • Progress continues on the property received by bequest. The property was listed for sale on October 1, 2025.
  • Maintenance of proposed building site and fencing at 421 N Whipple Street.